City Projects

Project Bid Information

Electrical Distribution System & Substation Infrastructure

Project Overview

*The distribution system is aged and much of it is nearing “end of life”

*Two of the three substations are at their end of life expectancy

*Build two new substations where each is capable of carrying the demand load and eliminate the third (Water Plant) substation.

*Increase the distribution voltage from 4160/2400VAC to 12470/7500VAC

*Replace all distribution transformers to accommodate new voltage level

*Overhead distribution service should be converted to underground

*Develop a strategic plan that can accomplish the CIP over the next 10 – 15 years

*Total proposed estimated cost - $15.4 million dollars.

Southside Drainage Improvements ~ New York Ave

Map.jpg

New Storm Sewer Installation with Complete Urban Street Reconstruction of New York Ave from 2nd through 6th Street 

The Army Corps of Engineers disclosed to the City that some homeowners on the south side of Breckenridge would still be required to purchase flood insurance as determined by a 100-year rain event due to internal drainage issues which were not part of the original flood protection project.

This project is to have additional storm drainage for rain water (100-year flood). Currently the levees are holding back the river water, but in return holding in the rain water. With the installation of the new culverts and storm sewers and by overtopping the roadways the water ultimately makes it's way to the levees, and pump, for discharge to the river. 

Funding:

Minnesota Flood Hazard Mitigation Grant #3000000499 through Department of Natural Resources (DNR)

As funding becomes available project will continue from 6th Street going east

 

07/07/20

Letter to Impacted Residents- Garbage Pickup

05/18/20

Revised Letter to Impacted Residents

05/07/20

Letter to Impacted Residents

April 12th, 19th, 26th of 2019

Advertisement for Bids

04/01/19

Resolution No. 12931-22

06/24/15

Interior Drainage Floodplain Mapping- South Side- from Army Corps

New York Avenue Extension Project

New York Ave Ext. Map.jpg

This project extends New York Avenue from 13th Street approximately 540 feet east and then from there south approximately 385 feet to Highway 75.  This extension would be a gravel road with possible water and sewer extensions planned, as well as storm sewer or the necessary culverts for drainage.

 

This road will be the access for future development.

05/04/20

Resolution No. 13041-34

Breckenridge Water Treatment Plant

As of October 1st, the New water plant has been the primary water producing facility for the city. The chemical feeding software has been fully debugged and the system ramps up and down based on the water flow. Currently, the plant runs at 700 gallons per minute (gpm) giving us one million gallons per day capacity. Currently, the city demand is around 240K to 280K gallons per day. The plant first started producing water back in mid-July. It has run several days a week during the debug and optimization phase contributing water to our overall distribution system and providing relief to the old plant.

           It has been a great project and is now time to get it into production full time. Cheers!

 Neil Crocker, Director of Public Services

Street Repair Process

      The following information is intended to help inform Breckenridge citizens of the process being used to prioritize street maintenance and repairs:

     In 2016, an Engineering firm (Widseth, Smith and Nolting) was hired to perform an assessment of every street and avenue in the city of Breckenridge. The assessment was very thorough and produced a map that is color coded for ease of understanding. The map shows each street and avenue in the city with an assigned color. The Map Key in the upper right-hand corner shows six different colors with a description for each. The city officials have further simplified the map into 3 colors: Green, Blue and Red.

     Blue = thin overlay

     Green = potential mill and overlay

     Red = total reconstruct

  The current efforts are to keep the Blue and Green streets/avenues from becoming Red. This is why you are seeing some streets getting repaved even though other streets are in worse condition. Those streets that are Red (needing total reconstruct) will cost quite a bit more to repair, and we are still working through the various funding source options. In the near term, efforts are being focused on repairing the streets/avenues that are still able to be salvaged with mill and/or overlay. The map is considered a guideline, but there may be some circumstances where some deviation from the map may be warranted based on current observations.

   The funding currently being used for mill and overlay street projects is coming from the general fund. This means that all tax payers share in the cost of maintaining the streets, as all tax payers use the streets.

   On the streets/avenues requiring total reconstruct, if water and/or sewer are replaced, home owners on that street/avenue will likely be assessed for a portion of the water and sewer.

   If you have specific questions regarding your street or Avenue, feel free to reach out to City Hall at 218-643-4681

Neil Crocker, Director of Public Services                                                    Renae Smith, City Administrator

Planned Street Project Map.jpg

Safe Routes to School

This project will begin in June 2019 and be completed in August 2022. This project is a complete system around the schools. This will include new sidewalks, parking lot NW of school, street crossing and painting, ADA compliant crossings, speed feedback signs, beacons, push-button crossings, auto gate for circle drive and more. The Breckenridge Active Living Committee has received a Transportation Alternative Grant for $225,000 to help with the funding of this project.

Camper/RV Rentals~ COMPLETE 2019

New camper/RV spots in Welles Memorial Park. Electric & water hook-ups are installed throughout the park. Campground reservation are available through City Hall (218)643-1431. For more information and photos of the sites.

Completed in 2019

Map of Welles Park.jpg

Highway 75 Path ~ COMPLETE 2018

    If you haven’t taken a stroll on the new Highway 75 pedestrian path, this would be a great time. The 1.15-mile path starts at Veteran’s Park /Family Community Center and takes you to CHI St. Francis. This path is 10 foot-wide, family friendly, and ADA compliant so that people of all ages and physical abilities can use it.

    Breckenridge Public Utility crews installated security lighting, which was made possible in part from an Otto Bremer Foundation grant.  Thank you, Otto Bremer!! With the installation of lighting, the path will not only be more useable 24 hours a day but will also be a welcoming entrance to the City.  Benches are installed along the path.

    Research shows that exercise and being outside can improve mood and overall health. It’s a great time of year to get outside and enjoy a walk on the path!